Telluride Mill Creek Prefab (PRV) Vault Installation
Project Description
Addendum No. 1 pdf – clarifying Bid Due Date: 4 pm on Thursday, April 30; Bid Forms pdf; Pay Items / Bid Schedule (excel spreadsheet); SMPA’s Construction Handbook; Site Plan (sheet 1 of 2); Email clarifying transformer connection in coordination with SMPA Documents available by owner.
2026-5 Contractor shall submit work & sequencing plan to install PRV off center from existing main (for example: set PRV, prep bends, thrust blocks, pipe joint connections and restraint back to main, perform outage, install tees and gate valves, thrust blocks and restraint to existing main, connect to existing water, perform start-up of PRV in coordination with Pipestone, disinfection testing in coordination with Public Works (approximately 60′ of new pipe install), perform outage, cut and cap existing 10-inch DIP. Documents available by owner. Bid Due Date: 4/28/2026